Brick Calculator

Estimate brick count from wall and brick dimensions, mortar allowance, and wastage.

Enter your values

Change any field. The result is recalculated on this device.

Formula, example and assumptions
Bricks including waste2,940

Wall dimensions and openings

m
m
m
m²

Brick size and mortar

mm
mm
mm
mm

Purchase allowance

%

Your result

Local calculation
Bricks including waste2,940

The brick count fills the wall volume after subtracting doors and windows, using your brick size and mortar joints. The purchase estimate rounds up after adding waste.

Wall thickness
0.2 m
Doors and windows area
2 m²
Mortar joint
10 mm
Wastage allowance (%)
5 %
See how this is calculated

Result breakdown

Bricks before waste
2,800
Net wall volume (m³)
5.6
Check the inputs and method

These are your current inputs, not the worked example further down the page.

Wall length
10 m
Wall height
3 m
Wall thickness
0.2 m
Doors and windows area
2 m²
Brick length
190 mm
Brick width
90 mm
Brick height
90 mm
Mortar joint
10 mm
Wastage allowance (%)
5 %

Method

Net wall volume V = (wall length × wall height − opening area) × wall thickness. Module volume M = (brick length + joint) × (brick width + joint) × (brick height + joint) ÷ 10⁹ for millimetre dimensions. Base bricks = ceiling(V ÷ M). Bricks with waste = ceiling((V ÷ M) × (1 + waste% ÷ 100)).

Read the worked example and assumptions

How this calculation works

Estimate brick units from the solid masonry volume after deducting door and window openings. The model expands each brick dimension by the mortar joint to approximate a repeating masonry module, then adds waste before rounding up. Measure net masonry thickness carefully; using a wall finish thickness or ignoring cavity construction can materially change the estimate.

Net wall volume V = (wall length × wall height − opening area) × wall thickness. Module volume M = (brick length + joint) × (brick width + joint) × (brick height + joint) ÷ 10⁹ for millimetre dimensions. Base bricks = ceiling(V ÷ M). Bricks with waste = ceiling((V ÷ M) × (1 + waste% ÷ 100)).

Worked example

This example uses illustrative inputs. Your current result is shown above.

A 10 m × 3 m wall, 0.20 m thick, with 2 m² of openings contains (30 − 2) × 0.20 = 5.6 m³ masonry. Bricks 190 × 90 × 90 mm with 10 mm joints form 0.002 m³ modules: 2,800 bricks before waste and 2,940 with 5% waste.

Assumptions and limits

  • Opening area is deducted through the full entered wall thickness and cannot exceed the gross wall area.
  • Uniform modules approximate the bond. Hollow units, cavities, lintels, reinforced columns and unusual joints need separate allowances; mortar volume itself is not output.

Questions people ask

Should brick dimensions already include mortar?

No. Enter actual brick dimensions and let the joint input add mortar allowance once.

Why is waste applied before rounding?

The model applies the percentage to the unrounded module count, then orders a whole number of bricks. Rounding the base first can overstate the final count near a boundary.